Rajasthan High Court
Arbitration

No Work Done, ₹653 Crore Award Falls: Rajasthan High Court Upholds Setting Aside of Award Against RSRTC

M/s Bhagwati Enterprises v. Rajasthan State Road Transport Corporation 2026:RJ-JP:34779-DB Decided 4 November 2026

Published: · NyayVidhan · 3 min read

In M/s Bhagwati Enterprises v. Rajasthan State Road Transport Corporation (2026:RJ-JP:34779-DB), the Rajasthan High Court dismissed a Section 37 appeal and upheld the setting aside of a 2011 arbitral award of ₹653.20 crore with 12% interest. The licensee never carried a single parcel and itself took back its security. Its loss of profit for three years rested on other bidders' offers, a term never assured and no proof of loss (paras 2, 18-19, 41-43).

No Work Done, ₹653 Crore Award Falls: Rajasthan High Court Upholds Setting Aside of Award Against RSRTC

Judgment Intelligence

Petition Dismissed
M/s Bhagwati Enterprises v. Rajasthan State Road Transport Corporation
2026:RJ-JP:34779-DB
D.B. Civil Miscellaneous Appeal No. 76/2025
Court
Rajasthan High Court
Date of Decision
4 November 2026
Bench
Justice Arun Monga and Justice Ashutosh Kumar
Relevant Acts & Sections
Arbitration and Conciliation Act, 1996 — Sections 28(3), 34 and 37; Indian Contract Act, 1872 — Sections 7, 62 and 73
Final Outcome

The Section 37 appeal was dismissed. The Commercial Court's order of 08.11.2024 was upheld and the arbitral award of 18.09.2011 stands set aside in full, as no part could be severed. Pending applications were disposed of, with no order as to costs (paras 40, 42-43).

Source Rajasthan High Court, hcraj.nic.in — judgment pronounced on 4 November 2026

Key holdings

  1. Section 34 objections filed before 23.10.2015 are governed by the unamended provision and the Saw Pipes line on public policy (para 13).
  2. Asking for and receiving back the security, after rejecting the counter offer, showed the licensee was not ready to perform (paras 18-19, 21).
  3. Where the tender assured one year and renewal depended on performance, profit for three years ignored a binding term (paras 24-28).
  4. Bids made by others in later tenders are no proof of the claimant's own loss of profit (paras 33-35).

Judgment digest by NyayVidhan: a summary of the court's judgment, not its text. The judgment itself is the authoritative version.

Brief Facts

In 2005 RSRTC accepted the appellant's bid to be sole licensee for carrying domestic articles and small goods on about 4,000 buses, at a monthly fee of ₹6,66,786 (paras 3-4, 7). The appellant signed the agreement with a handwritten note rejecting Clauses 29 and 30; RSRTC asked for a fresh agreement, the appellant sought and received its security back, and the work order was cancelled on 16.04.2005 (paras 7.4-7.6). A Sole Arbitrator appointed by the High Court awarded ₹6,53,20,86,367 with 12% interest on 18.09.2011, mostly as anticipated loss of profit (paras 5-6, 7.7-7.8). The Commercial Court set the award aside on 08.11.2024 (para 7.9).

Court's Findings

Because RSRTC's objections were filed on 24.12.2011, the unamended Section 34 applied, following Ssangyong, with public policy as explained in Saw Pipes, Western Geco and Associate Builders (para 13). The Court did not reopen the finding of a concluded contract, but held that under Section 62 of the Contract Act parties may end a contract by conduct; a licensee who asks for its security back is not ready and willing to perform, and cannot approbate and reprobate (paras 16-20, citing R.N. Gosain). Leaving out that vital evidence made the award perverse (para 21). Clause 21 of the tender assured only one year, so awarding three years' profit ignored a binding term under Section 28(3), which is patent illegality (paras 24-28). Relying on Kailash Nath, Unibros and Batliboi, the Court held that loss must be proved; other bidders' offers in later tenders proved nothing, and an award about 272 times the three-year licence fee was a windfall that shocks the conscience (paras 31, 35-38). Severance under Gayatri Balasamy was not possible (paras 39-40).

Legal Principle

A party that takes back its own security and walks away from a contract cannot claim profits for the full term. Loss of profit in arbitration needs credible proof; an award resting on others' bids, for a term never assured and wholly out of proportion to the bargain, conflicts with public policy (paras 19-20, 31, 38).

NyayVidhan's view · Practice note

Why It Matters

The Court applied the unamended Section 34 because RSRTC's objections were filed in 2011, so the public-policy heads were read as Saw Pipes and Associate Builders framed them (paras 13-14). It left untouched the finding that a concluded contract existed (para 16). On disproportion, the Bench followed its earlier judgment in Jaipur Development Authority v. Rohan Rahdeeo Rajasthan Infra Project Ltd. (para 30). For a Rajasthan High Court ruling, not cited here, on the narrow scope of a Section 37 appeal, see Chief Engineer (West), CAD, Bikaner v. Mitharwal Brothers; for a Supreme Court ruling, also not cited, restoring an award that a High Court had cut down, see Marino Dredgeco v. Port of Kolkata.

Editorial comment by the NyayVidhan Editorial Desk. It is not part of the Court's judgment and is not legal advice.

Precedents Relied Upon

  1. Associate Builders v. Delhi Development Authority (2015) 3 SCC 49 (Supreme Court of India)
    Relied Upon Discussed at ¶ 8, 13, 21, 27, 38

    Under the pre-2015 law, an award that ignores vital evidence is perverse and one that ignores a binding term of the contract is patently illegal; the Court read the public-policy heads as laid down there (paras 13, 21, 27, 38).

  2. MMTC Ltd. v. Vedanta Ltd. (2019) 4 SCC 163 (Supreme Court of India)
    Relied Upon Discussed at ¶ 8, 12

    A Section 34 court does not sit in appeal over an award, and under Section 37 the appellate court only examines whether the Section 34 court stayed within its limits (para 12).

  3. Ssangyong Engineering and Construction Co. Ltd. v. National Highways Authority of India (2019) 15 SCC 131 (Supreme Court of India)
    Relied Upon Discussed at ¶ 8, 13

    The amended Section 34 applies only to applications filed on or after 23.10.2015, so objections filed on 24.12.2011 are governed by the unamended provision (para 13).

View all precedents (20)
  1. Reliance Infrastructure Ltd. v. State of Goa (2024) 1 SCC 479 (Supreme Court of India)
    Referred To Discussed at ¶ 8

    Cited by the appellant on the narrow scope of Section 34 (para 8); the Court accepted the general principles but held that limited review is not no review (paras 12-13).

  2. National Fertilizers Ltd. v. Puran Chand Nangia (2000) 8 SCC 343 (Supreme Court of India)
    Referred To Discussed at ¶ 8.1

    Cited by the appellant for the rule that a concluded contract cannot be defeated by unilateral cancellation (para 8.1); the Court left the concluded-contract finding untouched and decided the appeal on the appellant's conduct (para 16).

  3. A.T. Brij Paul Singh v. State of Gujarat (1984) 4 SCC 59 (Supreme Court of India)
    Distinguished Discussed at ¶ 8.3, 33

    A works contract where part of the work was done and damages were 15% of the balance work; it supports a broad evaluation of a reasonable margin, not hundreds of crores on bids by strangers (para 33).

  4. Dwaarka Das v. State of Madhya Pradesh (1999) 3 SCC 500 (Supreme Court of India)
    Distinguished Discussed at ¶ 8.3, 33

    A works contract where damages were 10% of the contract value, unlike a licensee who was to pay RSRTC a fee (para 33).

  5. Mohd. Salamatullah v. Government of Andhra Pradesh (1977) 3 SCC 590 (Supreme Court of India)
    Distinguished Discussed at ¶ 8.3, 33

    A works contract in which a modest percentage was applied as damages; it does not support the award here (para 33).

  6. McDermott International Inc. v. Burn Standard Co. Ltd. (2006) 11 SCC 181 (Supreme Court of India)
    Distinguished Discussed at ¶ 8.3, 34

    The choice of formula is for the arbitrator, but every formula needs proven inputs; there the work had been done and costs incurred, while here the inputs were other parties' bids (para 34).

  7. Gayatri Balasamy v. ISG Novasoft Technologies Ltd. 2025 SCC OnLine SC 986 (Supreme Court of India)
    Relied Upon Discussed at ¶ 8.5, 39-40

    A court may set aside part of an award only where the valid and invalid parts are truly separable, and cannot reassess the merits or work out a fresh figure; nothing here could be severed (paras 39-40).

  8. Oil and Natural Gas Corporation Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705 (Supreme Court of India)
    Relied Upon Discussed at ¶ 9.2, 13, 38

    An award so unfair and unreasonable that it shocks the conscience of the court is against the public policy of India; the pre-2015 law applied to these objections (paras 13, 38).

  9. Unibros v. All India Radio 2023 SCC OnLine SC 1366 (Supreme Court of India)
    Relied Upon Discussed at ¶ 9.2, 31-32, 34

    A claim for loss of profit in arbitration needs credible evidence; a formula cannot be applied in a vacuum, and an award resting on no evidence on that head is patently illegal (paras 31-32, 34).

  10. Batliboi Environmental Engineers Ltd. v. Hindustan Petroleum Corporation Ltd. (2024) 2 SCC 375 (Supreme Court of India)
    Relied Upon Discussed at ¶ 9.2, 31-32

    Damages cannot be whimsical or disproportionate and must rest on an intelligible factual basis (paras 31-32).

  11. Delhi Metro Rail Corporation Ltd. v. Delhi Airport Metro Express Pvt. Ltd. (2024) 6 SCC 357 (Supreme Court of India)
    Relied Upon Discussed at ¶ 9.2, 21

    An award that leaves out vital evidence is perverse; the principle was applied in that case (para 21).

  12. Punjab State Civil Supplies Corporation Ltd. v. Sanman Rice Mills 2024 SCC OnLine SC 2632 (Supreme Court of India)
    Relied Upon Discussed at ¶ 12

    Under Section 37 the appellate court is narrower still and examines whether the Section 34 court stayed within its limits (para 12).

  13. ONGC Ltd. v. Western Geco International Ltd. (2014) 9 SCC 263 (Supreme Court of India)
    Relied Upon Discussed at ¶ 13-14

    Part of the pre-2015 law on public policy, including a judicial approach, natural justice and reasonableness, that governs these objections (paras 13-14).

  14. R.N. Gosain v. Yashpal Dhir (1992) 4 SCC 683 (Supreme Court of India)
    Relied Upon Discussed at ¶ 20

    A person cannot approbate and reprobate or take a benefit under an arrangement and then deny its basis; having taken the refund, the appellant cannot claim three years of profit (para 20).

  15. State of Chhattisgarh v. Sal Udyog Pvt. Ltd. (2022) 2 SCC 275 (Supreme Court of India)
    Relied Upon Discussed at ¶ 27

    Ignoring a binding term of the contract is patent illegality, reiterating Associate Builders (para 27).

  16. Jaipur Development Authority v. Rohan Rahdeeo Rajasthan Infra Project Ltd. D.B. Civil Miscellaneous Appeal No. 1560/2025, 2026:RJ-JP:30253-DB (Rajasthan High Court) 2026:RJ-JP:30253-DB
    Followed Discussed at ¶ 30-31

    An award bearing no rational proportion to the loss shocks the conscience and is vitiated independently; the Court quoted its paras 79-81.3 and held the disproportion here also vitiates the whole award (paras 30-31).

  17. Kailash Nath Associates v. Delhi Development Authority (2015) 4 SCC 136 (Supreme Court of India)
    Relied Upon Discussed at ¶ 31

    Damage or loss caused by the breach is a sine qua non for compensation under the Contract Act, and where loss can be proved it must be proved (para 31).