Judgment Intelligence
Petition Dismissed- Court
- Rajasthan High Court
- Date of Decision
- 4 November 2026
- Bench
- Justice Arun Monga and Justice Ashutosh Kumar
- Relevant Acts & Sections
- Arbitration and Conciliation Act, 1996 — Sections 28(3), 34 and 37; Indian Contract Act, 1872 — Sections 7, 62 and 73
The Section 37 appeal was dismissed. The Commercial Court's order of 08.11.2024 was upheld and the arbitral award of 18.09.2011 stands set aside in full, as no part could be severed. Pending applications were disposed of, with no order as to costs (paras 40, 42-43).
Source Rajasthan High Court, hcraj.nic.in — judgment pronounced on 4 November 2026
Key holdings
- Section 34 objections filed before 23.10.2015 are governed by the unamended provision and the Saw Pipes line on public policy (para 13).
- Asking for and receiving back the security, after rejecting the counter offer, showed the licensee was not ready to perform (paras 18-19, 21).
- Where the tender assured one year and renewal depended on performance, profit for three years ignored a binding term (paras 24-28).
- Bids made by others in later tenders are no proof of the claimant's own loss of profit (paras 33-35).
Judgment digest by NyayVidhan: a summary of the court's judgment, not its text. The judgment itself is the authoritative version.
Brief Facts
Court's Findings
Legal Principle
NyayVidhan's view · Practice note
Why It Matters
The Court applied the unamended Section 34 because RSRTC's objections were filed in 2011, so the public-policy heads were read as Saw Pipes and Associate Builders framed them (paras 13-14). It left untouched the finding that a concluded contract existed (para 16). On disproportion, the Bench followed its earlier judgment in Jaipur Development Authority v. Rohan Rahdeeo Rajasthan Infra Project Ltd. (para 30). For a Rajasthan High Court ruling, not cited here, on the narrow scope of a Section 37 appeal, see Chief Engineer (West), CAD, Bikaner v. Mitharwal Brothers; for a Supreme Court ruling, also not cited, restoring an award that a High Court had cut down, see Marino Dredgeco v. Port of Kolkata.
Editorial comment by the NyayVidhan Editorial Desk. It is not part of the Court's judgment and is not legal advice.
Precedents Relied Upon
- Associate Builders v. Delhi Development Authority (2015) 3 SCC 49 (Supreme Court of India)
Under the pre-2015 law, an award that ignores vital evidence is perverse and one that ignores a binding term of the contract is patently illegal; the Court read the public-policy heads as laid down there (paras 13, 21, 27, 38).
- MMTC Ltd. v. Vedanta Ltd. (2019) 4 SCC 163 (Supreme Court of India)
A Section 34 court does not sit in appeal over an award, and under Section 37 the appellate court only examines whether the Section 34 court stayed within its limits (para 12).
- Ssangyong Engineering and Construction Co. Ltd. v. National Highways Authority of India (2019) 15 SCC 131 (Supreme Court of India)
The amended Section 34 applies only to applications filed on or after 23.10.2015, so objections filed on 24.12.2011 are governed by the unamended provision (para 13).
View all precedents (20)
- Reliance Infrastructure Ltd. v. State of Goa (2024) 1 SCC 479 (Supreme Court of India)
Cited by the appellant on the narrow scope of Section 34 (para 8); the Court accepted the general principles but held that limited review is not no review (paras 12-13).
- National Fertilizers Ltd. v. Puran Chand Nangia (2000) 8 SCC 343 (Supreme Court of India)
Cited by the appellant for the rule that a concluded contract cannot be defeated by unilateral cancellation (para 8.1); the Court left the concluded-contract finding untouched and decided the appeal on the appellant's conduct (para 16).
- A.T. Brij Paul Singh v. State of Gujarat (1984) 4 SCC 59 (Supreme Court of India)
A works contract where part of the work was done and damages were 15% of the balance work; it supports a broad evaluation of a reasonable margin, not hundreds of crores on bids by strangers (para 33).
- Dwaarka Das v. State of Madhya Pradesh (1999) 3 SCC 500 (Supreme Court of India)
A works contract where damages were 10% of the contract value, unlike a licensee who was to pay RSRTC a fee (para 33).
- Mohd. Salamatullah v. Government of Andhra Pradesh (1977) 3 SCC 590 (Supreme Court of India)
A works contract in which a modest percentage was applied as damages; it does not support the award here (para 33).
- McDermott International Inc. v. Burn Standard Co. Ltd. (2006) 11 SCC 181 (Supreme Court of India)
The choice of formula is for the arbitrator, but every formula needs proven inputs; there the work had been done and costs incurred, while here the inputs were other parties' bids (para 34).
- Gayatri Balasamy v. ISG Novasoft Technologies Ltd. 2025 SCC OnLine SC 986 (Supreme Court of India)
A court may set aside part of an award only where the valid and invalid parts are truly separable, and cannot reassess the merits or work out a fresh figure; nothing here could be severed (paras 39-40).
- Oil and Natural Gas Corporation Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705 (Supreme Court of India)
An award so unfair and unreasonable that it shocks the conscience of the court is against the public policy of India; the pre-2015 law applied to these objections (paras 13, 38).
- Unibros v. All India Radio 2023 SCC OnLine SC 1366 (Supreme Court of India)
A claim for loss of profit in arbitration needs credible evidence; a formula cannot be applied in a vacuum, and an award resting on no evidence on that head is patently illegal (paras 31-32, 34).
- Batliboi Environmental Engineers Ltd. v. Hindustan Petroleum Corporation Ltd. (2024) 2 SCC 375 (Supreme Court of India)
Damages cannot be whimsical or disproportionate and must rest on an intelligible factual basis (paras 31-32).
- Delhi Metro Rail Corporation Ltd. v. Delhi Airport Metro Express Pvt. Ltd. (2024) 6 SCC 357 (Supreme Court of India)
An award that leaves out vital evidence is perverse; the principle was applied in that case (para 21).
- Punjab State Civil Supplies Corporation Ltd. v. Sanman Rice Mills 2024 SCC OnLine SC 2632 (Supreme Court of India)
Under Section 37 the appellate court is narrower still and examines whether the Section 34 court stayed within its limits (para 12).
- ONGC Ltd. v. Western Geco International Ltd. (2014) 9 SCC 263 (Supreme Court of India)
Part of the pre-2015 law on public policy, including a judicial approach, natural justice and reasonableness, that governs these objections (paras 13-14).
- R.N. Gosain v. Yashpal Dhir (1992) 4 SCC 683 (Supreme Court of India)
A person cannot approbate and reprobate or take a benefit under an arrangement and then deny its basis; having taken the refund, the appellant cannot claim three years of profit (para 20).
- State of Chhattisgarh v. Sal Udyog Pvt. Ltd. (2022) 2 SCC 275 (Supreme Court of India)
Ignoring a binding term of the contract is patent illegality, reiterating Associate Builders (para 27).
- Jaipur Development Authority v. Rohan Rahdeeo Rajasthan Infra Project Ltd. D.B. Civil Miscellaneous Appeal No. 1560/2025, 2026:RJ-JP:30253-DB (Rajasthan High Court) 2026:RJ-JP:30253-DB
An award bearing no rational proportion to the loss shocks the conscience and is vitiated independently; the Court quoted its paras 79-81.3 and held the disproportion here also vitiates the whole award (paras 30-31).
- Kailash Nath Associates v. Delhi Development Authority (2015) 4 SCC 136 (Supreme Court of India)
Damage or loss caused by the breach is a sine qua non for compensation under the Contract Act, and where loss can be proved it must be proved (para 31).


