Latest
Thursday, October 22, 2026
Rajasthan High Court
Arbitration

Section 37 Appeal Is Not a Second Merits Review of an Arbitral Award: Rajasthan High Court

Published: · NyayVidhan

The Rajasthan High Court at Jodhpur dismissed the State's appeal under Section 37 of the Arbitration and Conciliation Act, 1996 against a District Judge's refusal to set aside an award refunding ₹60,000 of trench and diggi deductions with interest (paras 2.3, 10). It held that a Section 37 court checks only whether the Section 34 court kept within its statutory limits, and cannot reappraise evidence or reinterpret the contract because another view is possible (paras 6.4, 6.7, 9.17-9.18).

Section 37 Appeal Is Not a Second Merits Review of an Arbitral Award: Rajasthan High Court

Judgment Intelligence

Petition Dismissed
The Chief Engineer (West), CAD, Bikaner & Anr. v. M/s Mitharwal Brothers & Ors.
2026:RJ-JD:47934
S.B. Civil Miscellaneous Appeal No. 1721/2025
Court
Rajasthan High Court
Date of Decision
5 October 2026
Bench
Justice Farjand Ali
Relevant Acts & Sections
Arbitration and Conciliation Act, 1996 — Sections 34, 34(2A), 34(4), 37(1)(c)
Final Outcome

Appeal dismissed; the District Judge, Bikaner's order of 25.10.2024 in Civil Misc. Application No. 12/2019 dismissing the Section 34 objections to the award of 25.09.2018 affirmed; pending applications disposed of (paras 10-11).

Source Rajasthan High Court, hcraj.nic.in — order dated 05.10.2026

Key holdings

  1. Section 34 scrutinises the award; Section 37 scrutinises the Section 34 decision, not the dispute afresh (paras 6.7, 6.11).
  2. The Gayatri Balasamy power to modify an award is confined and did not apply to a challenge on the merits (paras 7.3, 8.1-8.3).
  3. Whether trench and diggi facilities existed was a factual question decided by the Arbitrator and not open to reappraisal (paras 9.2-9.4).
  4. No-protest, final-bill, interest and delay objections disclosed no ground under Section 34 (paras 9.5-9.9).

Judgment digest by NyayVidhan: a summary of the court's judgment, not its text. The judgment itself is the authoritative version.

Brief Facts

Under Contract No. 2 of 1995-96, the contractor firm was to manufacture and supply 37 lakh baked bricks to the State authorities (para 3). The Department made deductions under the contract's ‘G’ Schedule, on the premise that trench and diggi facilities were available at the site (para 2.1). The award of 25.09.2018 directed payment of ₹60,000 towards those deductions with simple interest at 6.5% per annum from 06.12.2004 (paras 2.2-2.3). The State's Section 34 objections relied on the ‘G’ Schedule, the firm's acceptance of the additional work order without protest and of the final bill, the absence of an interest clause, and the prolonged proceedings (paras 2.4-2.5). The District Judge, Bikaner dismissed them on 25.10.2024 (paras 2.8, 10).

Court's Findings

The Court held that Section 34 is not an appeal: the Court does not reweigh evidence or displace a contractual interpretation reasonably possible on the material, and public policy and patent illegality do not reopen every finding (paras 5, 5.4-5.6). Following MMTC Ltd. v. Vedanta Ltd., Section 37 cannot travel beyond Section 34; it examines whether the Section 34 court correctly exercised its jurisdiction (paras 6.4, 6.7, 6.10). The limited power to modify an award recognised in Gayatri Balasamy did not arise, as there was no clerical error, severable portion or post-award interest correction (paras 7.3, 8-8.2). The deduction clause depended on a factual condition: the Arbitrator found the facilities were not available as asserted, the contractor having drawn water by its own tractor from the canal, and revisiting that would be reappraisal (paras 9.2-9.4). The District Judge's views that absence of protest was no absolute bar, and that Clause 17 contained no express stipulation extinguishing claims on acceptance of the final bill, were not shown to be legally impermissible (paras 9.5-9.6). No patent error was shown on interest, and mere duration was no ground (paras 9.7-9.9).

Legal Principle

Under Section 37 of the Arbitration and Conciliation Act, 1996, the appellate court examines whether the Section 34 court stayed within the statutory grounds, not the award's merits. A plausible view of facts or contract cannot be replaced merely because another view is possible; patent illegality must be apparent on the face of the award (paras 6.7, 9.11, 9.18).

Precedents Relied Upon

  1. MMTC Ltd. v. Vedanta Ltd. (2019) 4 SCC 163
    Applied Discussed at ¶ 6.4

    Interference under Section 37 cannot travel beyond the restrictions in Section 34; the appellate court only ascertains whether the Section 34 court acted within that provision.

  2. Applied Discussed at ¶ 7, 7.2, 7.3, 7.4, 7.7, 8.2, 8.3, 9.22

    The limited power to modify an award (severance, clerical or computational errors, post-award interest) does not permit reopening the merits; the challenge here fell outside it.

NyayVidhan
Court Judgments · 3 min read
Decided: October 5, 2026 Justice Farjand Ali
PDF
 Join our WhatsApp Group
✕

Try: POCSO, IBC, Electoral Bond, Article 370, NDPS Act, Bail Conditions, SC Contempt