Judgment Intelligence
Petition Allowed- Court
- Supreme Court of India
- Date of Decision
- 18 November 2026
- Bench
- Justices J.B. Pardiwala and K. Vinod Chandran
- Relevant Acts & Sections
- Arbitration and Conciliation Act, 1996 — Sections 34 and 37
Contractor's appeal allowed. The Calcutta High Court's Section 37 judgment is set aside and the arbitral award stands restored; the Port Trust's appeal is disposed of, as that judgment is already set aside (paras 15-16).
Source Supreme Court of India, www.sci.gov.in — judgment dated 18 November 2026 · Court's copy
Key holdings
- Additional re-dredging identical to the original work made a claim above 70% of the contract no ground to modify the award (para 7).
- ‘Shocking the conscience’ needs a substantive reason that blatantly brings out conflict with the most basic notions of morality or justice (paras 9-10).
- A quantification based on valid measurements and invoices has no severable ‘invalid’ portion (para 12).
- A Government entity as award debtor gets no special treatment on quantum (para 13).
- Batliboi, a damages case, did not apply to invoices for additional work (para 5).
Judgment digest by NyayVidhan: a summary of the court's judgment, not its text. The judgment itself is the authoritative version.
Brief Facts
Court's Findings
Legal Principle
NyayVidhan's view · Practice note
Why It Matters
The ruling keeps the public-policy ground narrow at the Section 37 stage. A Division Bench that finds an award neither perverse nor patently illegal cannot then trim it because the figure looks large against the contract value, or because a Government body has to pay (paras 8, 13). Where the additional work is of the same kind as the contracted work, its size alone proves nothing (para 7). On partial setting aside, read it with the Constitution Bench in Gayatri Balasamy v. M/s. ISG Novasoft Technologies Limited: severance needs a separable invalid portion, and one set of measurements and invoices has none (paras 11-12).
Editorial comment by the NyayVidhan Editorial Desk. It is not part of the Court's judgment and is not legal advice.
Precedents Relied Upon
Constitution Bench decision cited by both sides on the limits of interference with an award (paras 3-4). The Court took from it that an award can be set aside in part, but not where the ‘valid’ and ‘invalid’ portions are legally and practically inseparable or intertwined, and held that no question of severance arose here, since the quantification rested on valid measurements and invoices of one character (para 12).
- Batliboi Environmental Engineers Ltd. v. Hindustan Petroleum Corporation Ltd. (HPCL) (2024) 2 SCC 375
Relied on by the Port Trust to argue that the quantification of amounts should not be whimsical and absurd, resulting in a windfall or bounty. The Court held that it has no application, since it dealt with damages and not with invoices validly raised for additional work.
- Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of India (NHAI) (2019) 15 SCC 131
Relied on by the Division Bench. The Court read it as holding that, after the 2015 Amendment, an award cannot be interfered with because the Arbitrator did not adopt a judicial approach, and that conflict with the most basic notions of morality or justice applies only where the award shocks the conscience of the Court; those words need a substantive reason and cannot be applied as mere lip service.
View all precedents (5)
- Somdatt Builders–NCC–NEC (JV) v. National Highways Authority of India & Ors. (2025) 6 SCC 757
Held that a High Court exercising its extremely limited jurisdiction under Section 37 cannot set aside an arbitral award by merely using expressions such as ‘patent illegality’ or ‘shocking the conscience of the Court’; the Court found that the impugned judgment had used those words on the sole ground that the bills exceeded 70% of the original contract.
- Pam Developments Private Ltd. v. State of West Bengal (2019) 8 SCC 112
Required parties to an arbitration to be treated with equality, without special treatment for a Government entity, even on stay of a money decree in Section 34 proceedings. Relied on to hold that the quantum decided on valid material cannot be cut merely because the award debtor is a Government entity and the amount appears excessive.


