Rs 14 Crore Paid, Zonal Plan Work Not Done: Rajasthan High Court Seeks ACB, LSG Affidavits on Recovery

Sanjay Kumar Sharma v. State of Rajasthan Decided 18 November 2026

Published: · NyayVidhan · 3 min read

In Sanjay Kumar Sharma v. State of Rajasthan (D.B. Civil Writ Petition No. 9694/2024), the Rajasthan High Court at Jodhpur called the case "an eye opener for the genuine tax payers" (para 2). About Rs 14 crore of a Rs 21 crore tender for zonal development plans in Bikaner Division was paid to a private firm, yet nothing has been recovered. The Court directed the Director General, Anti Corruption Bureau and the Secretary, Local Self Department to file affidavits by 15 December 2026 (paras 11-12).

Rs 14 Crore Paid, Zonal Plan Work Not Done: Rajasthan High Court Seeks ACB, LSG Affidavits on Recovery

Judgment Intelligence

Interim Order
Sanjay Kumar Sharma v. State of Rajasthan
D.B. Civil Writ Petition No. 9694/2024
Court
Rajasthan High Court
Date of Decision
18 November 2026
Bench
Justice Vinit Kumar Mathur and Justice Sandeep Shah
Final Outcome

Interim order; the writ petition remains pending. Affidavits of the Director General, Anti Corruption Bureau and the Secretary, Local Self Department, Jaipur are due by 15 December 2026, failing which both must appear in person; listed on that date (paras 10-13).

Source Rajasthan High Court, hcraj.nic.in — order dated 18 November 2026

Key holdings

  1. About Rs 14 crore of a Rs 21 crore tender for Bikaner Division's zonal development plans was disbursed to respondent No. 9 (para 4).
  2. A Local Self Department report dated 2 January 2024 shows that the work under the tender was not undertaken (para 6).
  3. The earlier PIL was disposed of on 20 March 2024 with no finding on recoverability; the firm keeps all its defences (para 5).
  4. The ACB Director General and the Local Self Department Secretary must file affidavits on recovery and the investigation by 15 December 2026 (para 11).
  5. Interim order: if no affidavits are filed, both officers must appear in person on 15 December 2026 (paras 12-13).

Judgment digest by NyayVidhan: a summary of the court's judgment, not its text. The judgment itself is the authoritative version.

Brief Facts

The tender for preparing the zonal development plan of Bikaner Division went to M/s Green City Surveyors Private Limited (respondent No. 9). Of the tender amount of Rs 21 crore, about Rs 14 crore was disbursed to it (para 4). The petitioner's earlier public interest petition, D.B. Civil Writ Petition (P.I.L.) No. 2555/2022, was disposed of on 20 March 2024, leaving the State free to draw recovery proceedings and the firm free to raise all its defences (paras 4-5). In this second petition he says the money remains unrecovered despite several committee reports, and that an Anti Corruption Bureau case against officials has not moved beyond the FIR in five years (paras 3, 7-8).

Court's Findings

The Bench observed that persons entrusted with public works appear to be drawing sanctioned funds without completing the work, and that the steps taken by State officials "are falling way short in discharge of their official duties" (paras 2, 4). It noted that a report dated 2 January 2024, from the Deputy Director (Regional), Local Self Department, Bikaner, shows that respondent No. 9 did not undertake the work under its tender (para 6). The earlier orders it reproduced record that in September 2023 the Court had found it "outright shocking" that nothing had been done in a matter pending for over four years (para 4). The Additional Advocate General sought time to report on both issues, which was allowed (paras 9-10). The Court directed affidavits sworn by the Director General, Anti Corruption Bureau and the Secretary, Local Self Department, Jaipur, on the recovery and on the progress of the investigation (para 11).

Legal Principle

Where public money paid under a government contract stays unrecovered despite inquiry reports and an earlier disposal that left the State free to recover it, the High Court can keep the matter under watch and require the heads of the departments concerned to account on affidavit, with personal appearance as the consequence of default (paras 3, 11-12).

NyayVidhan's view · Practice note

Why It Matters

Nothing has yet been decided against the firm or any official. The earlier Bench left open whether the money is recoverable at all and preserved the firm’s right to be heard in any recovery proceedings (para 5); this order only calls for affidavits. What it adds is pressure on two heads of department, with personal appearance as the consequence if the affidavits are not filed by 15 December 2026 (paras 11-12). The High Court used the same lever recently in Prahlad Sharma v. Union of India; for a long-stalled investigation answered with policy directions, compare Jitendra Meena v. State of Rajasthan. Neither is cited in this order.

Editorial comment by the NyayVidhan Editorial Desk. It is not part of the Court's judgment and is not legal advice.