Judgment Intelligence
Petition Allowed- Court
- Supreme Court of India
- Date of Decision
- 18 November 2026
- Bench
- Justices J.B. Pardiwala and K. Vinod Chandran
- Relevant Acts & Sections
- Electricity Act, 2003 — Sections 2(16), 2(32), 2(72), 10, 29(4), 61, 79 and 178; Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 — Regulations 3(53) and 4(3), including 4(3)(ii); Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2023 (Pooling Station)
Appeals allowed. The impugned orders of APTEL in both appeals are set aside and the order of the CERC is restored (paras 50-51).
Source Supreme Court of India, www.sci.gov.in — judgment dated 18 November 2026 · Court's copy
Key holdings
- APTEL erred in finding the two LILOs unused; the generator's own pleadings before it admitted their use (paras 16, 46).
- A dedicated transmission line is the generating company's obligation under Sections 2(16) and 10 of the Electricity Act (para 22).
- Regulation 4(3)(ii) applies only when regular service is prevented, so the COD the CERC accepted needed no redetermination (paras 39, 41).
- The two LILOs are includable in the tariff as non-PoC from 04.01.2015 to the DTL's establishment on 27.10.2016 (para 49).
- The CERC passage on which APTEL built its ‘beneficial use’ concept only recorded TANGEDCO's contentions (para 48).
Judgment digest by NyayVidhan: a summary of the court's judgment, not its text. The judgment itself is the authoritative version.
Brief Facts
Court's Findings
Legal Principle
NyayVidhan's view · Practice note
Why It Matters
Generators that commission units before their dedicated lines should expect to pay, outside the PoC pool, for the CTU assets that carry their power in the meantime, even if the planned upstream system is late (paras 36, 45). A plea of ‘no beneficial use’ will fail where the generator's own pleadings admit evacuation through the asset (para 16). A transmission licensee can rely on the RLDC's trial-operation certificate for the COD, without a Regulation 4(3)(ii) application, when regular service was never prevented (paras 39-41). The generator's silence in the Standing Committee meetings and its absence before the CERC also counted against it (paras 13, 47).
Editorial comment by the NyayVidhan Editorial Desk. It is not part of the Court's judgment and is not legal advice.
Precedents Relied Upon
- Power Grid Corporation of India Limited v. Madhya Pradesh Power Transmission Company Limited and Ors. (2025) 8 SCC 705
Where the delay of another party left the CTU's commissioned assets idle, the CERC could fix the defaulting party's liability for transmission charges from the COD approved under Regulation 4(3)(ii), even without a regulation under Section 178. The Court held that this dictum squarely applies where the generating company failed to establish its dedicated transmission line in time, so the CERC rightly cast the charges for the period between the LILOs' COD and the DTL on it.
- PTC India Limited v. Central Electricity Regulatory Commission, Thr. Secretary (2010) 4 SCC 603
Relied on in the PGCIL decision: regulations under Section 178 are delegated legislation of general application, while orders under Section 79 are confined to existing regulations; a measure under Section 79(1) must conform to a regulation where one exists.
- Energy Watchdog v. Central Electricity Regulatory Commission and Ors. Etc. (2017) 14 SCC 80
Relied on in the PGCIL decision: Section 79(1) is the repository of the CERC's regulatory powers, to be exercised in conformity with regulations under Section 178 where they exist, and even otherwise despite a regulatory lacuna.