Wednesday, 18 November 2026
Supreme Court of India
Civil Law

Generator Liable for LILO Transmission Charges Until Its Dedicated Line Is Commissioned: Supreme Court

Power Grid Corporation of India Limited v. Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) & Ors. 2026 INSC 1237 Decided 18 November 2026

Published: · NyayVidhan · 3 min read

In Power Grid Corporation of India Limited v. Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) & Ors. (2026 INSC 1237), the Supreme Court held that the generating company must bear, as non-PoC charges, the transmission tariff for two LILOs at the Tuticorin Pooling Station from 04.01.2015 until its dedicated transmission line was established on 27.10.2016. It set aside APTEL's orders and restored the CERC order (paras 45, 49-50).

Generator Liable for LILO Transmission Charges Until Its Dedicated Line Is Commissioned: Supreme Court

Judgment Intelligence

Petition Allowed
Power Grid Corporation of India Limited v. Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) & Ors.
2026 INSC 1237
Civil Appeal Nos. 14780-14781 of 2025 with Civil Appeal No. 13153 of 2026
Court
Supreme Court of India
Date of Decision
18 November 2026
Bench
Justices J.B. Pardiwala and K. Vinod Chandran
Relevant Acts & Sections
Electricity Act, 2003 — Sections 2(16), 2(32), 2(72), 10, 29(4), 61, 79 and 178; Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 — Regulations 3(53) and 4(3), including 4(3)(ii); Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2023 (Pooling Station)
Final Outcome

Appeals allowed. The impugned orders of APTEL in both appeals are set aside and the order of the CERC is restored (paras 50-51).

Source Supreme Court of India, www.sci.gov.in — judgment dated 18 November 2026 · Court's copy

Key holdings

  1. APTEL erred in finding the two LILOs unused; the generator's own pleadings before it admitted their use (paras 16, 46).
  2. A dedicated transmission line is the generating company's obligation under Sections 2(16) and 10 of the Electricity Act (para 22).
  3. Regulation 4(3)(ii) applies only when regular service is prevented, so the COD the CERC accepted needed no redetermination (paras 39, 41).
  4. The two LILOs are includable in the tariff as non-PoC from 04.01.2015 to the DTL's establishment on 27.10.2016 (para 49).
  5. The CERC passage on which APTEL built its ‘beneficial use’ concept only recorded TANGEDCO's contentions (para 48).

Judgment digest by NyayVidhan: a summary of the court's judgment, not its text. The judgment itself is the authoritative version.

Brief Facts

PGCIL, the Central Transmission Utility, built two LILOs of the Tuticorin JV-Madurai 400kV D/C line at the Tuticorin Pooling Station, commissioned on 04.01.2015 and 08.01.2015 (opening paragraph). Moxie Power Generation Limited (formerly Coastal Energen Private Limited) began generating on 23.12.2014 and evacuated power through a temporary LILO, as its dedicated transmission line (DTL) came up only on 27.10.2016 (paras 17, 19, 35). The CERC accepted the COD of both LILOs and held the generator liable for their charges till its DTL was commissioned (paras 11, 13). APTEL, examining non-PoC charges of Rs.15,43,26,909/-, found the LILOs a permanent part of the plan but not put to use; on PGCIL's review it remanded the COD to the CERC (para 14).

Court's Findings

The Court found the LILOs in use. Power on the Tuticorin JV-Madurai line, once intercepted at the Loop-In, took the path of least resistance through the Pooling Station and back, and the generator had itself told APTEL that it was using the Pooling Station, seeking only PoC sharing, which could not be raised before commissioning its DTL (para 16). Under Sections 2(16) and 10 of the Electricity Act the DTL is the generating station's obligation (para 22). The LILOs, provided for in the BPTA and the 30th Standing Committee decision, were an integral part of the system and operated as the upstream path, so the late Tuticorin-Salem line did not affect evacuation and the DTL delay assumed significance (paras 32, 35-36). Regulation 4(3)(ii) of the 2014 Tariff Regulations applies only when regular service is prevented for reasons not attributable to the transmission licensee; here there was no impediment, and the COD accepted on the RLDC certificate of successful trial operation needed no redetermination. Though the time over-run was not condoned, liability runs from the LILOs' COD (paras 39-41). Applying the PGCIL decision, the CERC rightly cast it on the generator (para 45).

Legal Principle

Under the 2014 Tariff Regulations, a transmission element in regular service after a successful trial operation certified by the RLDC takes its COD under Regulation 4(3); Regulation 4(3)(ii) is for cases where regular service is prevented. A generator that delays its dedicated transmission line bears the charges of the CTU's assets used meanwhile (paras 39-40, 45).

NyayVidhan's view · Practice note

Why It Matters

Generators that commission units before their dedicated lines should expect to pay, outside the PoC pool, for the CTU assets that carry their power in the meantime, even if the planned upstream system is late (paras 36, 45). A plea of ‘no beneficial use’ will fail where the generator's own pleadings admit evacuation through the asset (para 16). A transmission licensee can rely on the RLDC's trial-operation certificate for the COD, without a Regulation 4(3)(ii) application, when regular service was never prevented (paras 39-41). The generator's silence in the Standing Committee meetings and its absence before the CERC also counted against it (paras 13, 47).

Editorial comment by the NyayVidhan Editorial Desk. It is not part of the Court's judgment and is not legal advice.

Precedents Relied Upon

  1. Power Grid Corporation of India Limited v. Madhya Pradesh Power Transmission Company Limited and Ors. (2025) 8 SCC 705
    Applied Discussed at ¶ 42, 45

    Where the delay of another party left the CTU's commissioned assets idle, the CERC could fix the defaulting party's liability for transmission charges from the COD approved under Regulation 4(3)(ii), even without a regulation under Section 178. The Court held that this dictum squarely applies where the generating company failed to establish its dedicated transmission line in time, so the CERC rightly cast the charges for the period between the LILOs' COD and the DTL on it.

  2. PTC India Limited v. Central Electricity Regulatory Commission, Thr. Secretary (2010) 4 SCC 603
    Referred To Discussed at ¶ 43, 44

    Relied on in the PGCIL decision: regulations under Section 178 are delegated legislation of general application, while orders under Section 79 are confined to existing regulations; a measure under Section 79(1) must conform to a regulation where one exists.

  3. Energy Watchdog v. Central Electricity Regulatory Commission and Ors. Etc. (2017) 14 SCC 80
    Referred To Discussed at ¶ 45

    Relied on in the PGCIL decision: Section 79(1) is the repository of the CERC's regulatory powers, to be exercised in conformity with regulations under Section 178 where they exist, and even otherwise despite a regulatory lacuna.

Join our WhatsApp Group
✕

Try: POCSO, IBC, Electoral Bond, Article 370, NDPS Act, Bail Conditions, SC Contempt