Judgment Intelligence
Petition Allowed- Court
- Supreme Court of India
- Date of Decision
- 17 November 2026
- Bench
- Justice P.S. Narasimha and Justice Alok Aradhe
- Relevant Acts & Sections
- Indian Contract Act, 1872 — Section 73 (in distinguishing A.T. Brij Paul Singh, para 9)
Appeal allowed. The direction to pay Rs. 21,59,242/- as compensation is quashed and set aside, the rest of the High Court's judgment of 01.09.2025 is upheld, and the successful bidder may proceed under the contract; no costs (paras 10-11).
Source Supreme Court of India, www.sci.gov.in — order dated 17 November 2026 · Court's copy
Key holdings
- The Rs. 21,59,242/- compensation direction was quashed; the rest of the High Court's judgment stands (para 10).
- That all bidders could have been asked to revise their bids is not a finding of illegality or arbitrariness (para 9).
- The L2 bidder had no legitimate right to be called for negotiation (para 9).
- Compensation went beyond the relief prayed for and had no foundation in the pleadings (para 9).
- A.T. Brij Paul Singh, on loss of profit after rescission of a concluded contract, does not apply where no contract was awarded (para 9).
Judgment digest by NyayVidhan: a summary of the court's judgment, not its text. The judgment itself is the authoritative version.
Brief Facts
Court's Findings
Legal Principle
NyayVidhan's view · Practice note
Why It Matters
Unsuccessful bidders should note the limits this order draws: a writ petition against a work order is not a claim for damages, and compensation cannot be granted where no foundation is laid in the pleadings and the authority had no occasion to contest it (para 9). Loss-of-profit damages of the kind awarded for wrongful rescission presuppose a concluded contract (para 9). For tendering authorities, a finding that a process could have been run better is not a finding of illegality (para 9). The order was passed without any appearance for the unsuccessful bidder (para 8).
Editorial comment by the NyayVidhan Editorial Desk. It is not part of the Court's judgment and is not legal advice.
Precedents Relied Upon
- A.T. Brij Paul Singh & Bros. v. State of Gujarat AIR 1984 SC 1703
Relied on by the High Court to estimate profit in a works contract at 15% of the value of the work. The Court held that decision concerned damages under Section 73 of the Indian Contract Act, 1872 for wrongful rescission of a concluded works contract, where loss of profit was a natural consequence of the breach; no contract was awarded to the unsuccessful bidder, so there was no loss of profit capable of assessment.