Writ Court That Finds Tender Process Valid Cannot Award Compensation to Losing Bidder: Supreme Court

Meghalaya Power Generation Corporation Ltd. (MePGCL) v. Odimar Syiemsad and Ors. Decided 17 November 2026

Published: · NyayVidhan · 3 min read

In Meghalaya Power Generation Corporation Ltd. (MePGCL) v. Odimar Syiemsad and Ors., the Supreme Court set aside a Meghalaya High Court direction to pay Rs. 21,59,242/- as compensation to an unsuccessful bidder. A writ court that finds the decision-making process valid cannot impose monetary liability on a government undertaking because that process caused the bidder injustice, the Court said. The rest of the High Court's judgment stands, and the successful bidder may proceed with the contract (paras 9-10).

Writ Court That Finds Tender Process Valid Cannot Award Compensation to Losing Bidder: Supreme Court

Judgment Intelligence

Petition Allowed
Meghalaya Power Generation Corporation Ltd. (MePGCL) v. Odimar Syiemsad and Ors.
Civil Appeal No. ___ of 2026 (arising out of SLP (C) No. 31342 of 2025)
Court
Supreme Court of India
Date of Decision
17 November 2026
Bench
Justice P.S. Narasimha and Justice Alok Aradhe
Relevant Acts & Sections
Indian Contract Act, 1872 — Section 73 (in distinguishing A.T. Brij Paul Singh, para 9)
Final Outcome

Appeal allowed. The direction to pay Rs. 21,59,242/- as compensation is quashed and set aside, the rest of the High Court's judgment of 01.09.2025 is upheld, and the successful bidder may proceed under the contract; no costs (paras 10-11).

Source Supreme Court of India, www.sci.gov.in — order dated 17 November 2026 · Court's copy

Key holdings

  1. The Rs. 21,59,242/- compensation direction was quashed; the rest of the High Court's judgment stands (para 10).
  2. That all bidders could have been asked to revise their bids is not a finding of illegality or arbitrariness (para 9).
  3. The L2 bidder had no legitimate right to be called for negotiation (para 9).
  4. Compensation went beyond the relief prayed for and had no foundation in the pleadings (para 9).
  5. A.T. Brij Paul Singh, on loss of profit after rescission of a concluded contract, does not apply where no contract was awarded (para 9).

Judgment digest by NyayVidhan: a summary of the court's judgment, not its text. The judgment itself is the authoritative version.

Brief Facts

On 04.07.2023 the Corporation, a government undertaking, invited tenders for a multipurpose indoor stadium in East Khasi Hills (paras 2-3). Four of the five technically qualified bidders quoted the same lowest amount; respondent no.1 quoted Rupee 1.34 more and was declared L2 (para 3). After the Tender Committee met the lowest bidders, three withdrew and a work order issued to the successful bidder on 15.02.2024 (para 4). A Single Judge, finding collusion, quashed the work order (para 5). On 01.09.2025 the Division Bench found no cartel and no illegality in the award, but held that all five bidders ought to have been called and awarded the unsuccessful bidder Rs. 21,59,242/-, at 7.5% of the value of the work (para 6).

Court's Findings

The direction to pay compensation contradicted the High Court's own findings: no cartelisation, a proper technical evaluation, no impropriety by the Tender Committee, and an award neither illegal nor improper (para 9). That all five bidders could have been asked to revise their bids was ‘at best, a view on what might have been a better course’, not a finding of illegality or arbitrariness (para 9). A bidder has a right to fair consideration of its bid, and no breach of that right was found (para 9). The successful bidder was the lowest tenderer, so the unsuccessful bidder had no legitimate right to be called for negotiation; even an established legitimate expectation does not by itself give rise to a claim for damages in a writ petition (para 9). The writ petition sought only the quashing of the work order; no foundation for compensation was laid in the pleadings, so the Corporation had no occasion to contest it (para 9). A.T. Brij Paul Singh concerned damages under Section 73 of the Indian Contract Act, 1872 for wrongful rescission of a concluded works contract; here no contract was awarded, so there was no loss of profit capable of assessment (para 9).

Legal Principle

A writ court that finds a tender's decision-making process valid cannot simultaneously impose monetary liability on a government undertaking on the premise that the same process caused injustice to an unsuccessful bidder; a legitimate expectation, even if established, does not by itself give rise to a claim for damages in a writ petition (para 9).

NyayVidhan's view · Practice note

Why It Matters

Unsuccessful bidders should note the limits this order draws: a writ petition against a work order is not a claim for damages, and compensation cannot be granted where no foundation is laid in the pleadings and the authority had no occasion to contest it (para 9). Loss-of-profit damages of the kind awarded for wrongful rescission presuppose a concluded contract (para 9). For tendering authorities, a finding that a process could have been run better is not a finding of illegality (para 9). The order was passed without any appearance for the unsuccessful bidder (para 8).

Editorial comment by the NyayVidhan Editorial Desk. It is not part of the Court's judgment and is not legal advice.

Precedents Relied Upon

  1. A.T. Brij Paul Singh & Bros. v. State of Gujarat AIR 1984 SC 1703
    Distinguished Discussed at ¶ 6, 9

    Relied on by the High Court to estimate profit in a works contract at 15% of the value of the work. The Court held that decision concerned damages under Section 73 of the Indian Contract Act, 1872 for wrongful rescission of a concluded works contract, where loss of profit was a natural consequence of the breach; no contract was awarded to the unsuccessful bidder, so there was no loss of profit capable of assessment.