Judgment Intelligence
Interim Order- Court
- Supreme Court of India
- Date of Decision
- 6 November 2026
- Bench
- Chief Justice Surya Kant, Justice Joymalya Bagchi and Justice V. Mohana
- Relevant Acts & Sections
- Van (Sanrakshan Evam Samvardhan) Adhiniyam, 1980
Interim order; the suo motu petition remains pending. Mathura applications allowed: 44 trees may be felled on conditions (para 7). Bharatpur road applications disposed of: felling permitted once the CEC reports completed afforestation (paras 13-16). Other applications listed on 19.11.2026 (paras 17-24).
Source Supreme Court of India, www.sci.gov.in — order dated 6 November 2026 · Court's copy
Key holdings
- Mathura Military Station may fell 44 of the 60 trees sought, on the CEC's conditions, including Rs. 1,00,000 for each additional tree felled or damaged (paras 3, 7).
- The CEC found all 1,550 saplings present, alive and healthy before permission was given (paras 5, 7).
- Bharatpur-Bayana-Gangapur-Bhadoti Road: felling follows the Forest Department's compensatory afforestation and a CEC compliance report, within two months (paras 13-14).
- Tundla-Awagarh Road (739 trees): the CEC must report on approval under the Van (Sanrakshan Evam Samvardhan) Adhiniyam, 1980 and the road's width (paras 18-19).
- UPSIDA's, PGTL's, the Railways' and the Ministry of Defence's applications return on 19.11.2026 (paras 17, 22-24).
Judgment digest by NyayVidhan: a summary of the court's judgment, not its text. The judgment itself is the authoritative version.
Brief Facts
Court's Findings
Legal Principle
NyayVidhan's view · Practice note
Why It Matters
For agencies seeking to fell trees in the Taj Trapezium Zone, this order shows the plantation comes first and is checked before the trees go. At Mathura, permission followed only after the CEC found 1,550 saplings alive, against 44 trees (paras 5, 7). For the Bharatpur road, the Corporation's statement that Rs.1,07,33,630 had been deposited did not settle the matter: the Court directed the compensatory afforestation to be carried out and inspected first (paras 12-13). The permission also carries continuing duties, such as five years' maintenance and Rs. 1,00,000 for each extra tree at Mathura (paras 3, 6). The remaining applications return on 19.11.2026 (paras 17-24).
Editorial comment by the NyayVidhan Editorial Desk. It is not part of the Court's judgment and is not legal advice.