Judgment Intelligence
Petition Allowed- Court
- Supreme Court of India
- Date of Decision
- 20 November 2026
- Bench
- Justices Vikram Nath and Aparesh Kumar Singh
- Relevant Acts & Sections
- Constitution of India — Article 227 (petition before the High Court)
Appeal allowed. The Delhi High Court's order of 23.10.2024 and the National Commission's order of 07.06.2024 are set aside; the delay in filing Revision Petition No. 1621 of 2022 is condoned and the revision restored for decision on merits after hearing the parties (paras 10-11).
Source Supreme Court of India, www.sci.gov.in — judgment dated 20 November 2026 · Court's copy
Key holdings
- The length of delay is not decisive; the acceptability of the explanation is the relevant consideration (para 6).
- With the Covid-19 exclusion of 15.03.2020 to 28.02.2022, only 95 days of DDA's delay needed explanation (para 7).
- Change of counsel or internal procedures cannot by themselves justify every delay, but the steps are weighed together (para 8).
- The Court condoned the delay while expressly not approving DDA's lack of diligence (para 9).
- No opinion was expressed on the merits of the allotment dispute; all contentions are left open (para 11).
Judgment digest by NyayVidhan: a summary of the court's judgment, not its text. The judgment itself is the authoritative version.
Brief Facts
Court's Findings
Legal Principle
NyayVidhan's view · Practice note
Why It Matters
An authority seeking condonation should set out each step it took, such as the administrative approval, the engagement of panel counsel and the date the certified copy was obtained. The Court weighed those steps together and found nothing deliberate, while recording that a change of counsel or internal procedures cannot by themselves justify every delay (para 8). Where the Covid-19 exclusion applies, only the delay left after excluding 15.03.2020 to 28.02.2022 needs explaining (para 7). On restoration, the National Commission is to decide the revision on merits after hearing the parties; the Supreme Court expressed no view on the allotment dispute (para 11).
Editorial comment by the NyayVidhan Editorial Desk. It is not part of the Court's judgment and is not legal advice.
Precedents Relied Upon
- Collector, Land Acquisition, Anantnag and Another v. Mst. Katiji and Others (1987) 2 SCC 107
The expression ‘sufficient cause’ must receive a liberal interpretation so as to advance substantial justice. Relied on for the settled principles of condonation of delay, applied to find sufficient cause for DDA's delay in filing its revision petition before the National Commission.
- N. Balakrishnan v. M. Krishnamurthy (1998) 7 SCC 123
The length of delay is not decisive; the acceptability of the explanation furnished is the relevant consideration. Relied on, with Katiji, for a pragmatic and justice-oriented approach that does not render the requirement of sufficient cause meaningless.
- In Re: Cognizance for Extension of Limitation Suo Motu Writ Petition (Civil) No. 3 of 2020
The period from 15.03.2020 to 28.02.2022 was directed to be excluded for computing limitation. Applied to exclude a substantial part of the 512 days reported for DDA's revision petition, as the National Commission itself acknowledged, leaving 95 days to be explained.



