Explanation for Delay Must Be Weighed Cumulatively: Supreme Court Restores DDA's Consumer Revision

Delhi Development Authority v. Sudarshan Manjhi & Ors. 2026 INSC 1254 Decided 20 November 2026

Published: · NyayVidhan · 3 min read

In Delhi Development Authority v. Sudarshan Manjhi (2026 INSC 1254), the Supreme Court held that DDA had shown sufficient cause for the 95-day delay, left after the Covid-19 exclusion, in filing its revision petition before the National Commission. Weighing the administrative and procedural steps cumulatively, it called the Commission's approach unduly restrictive, condoned the delay while disapproving DDA's lack of diligence, set aside the Commission's and the Delhi High Court's orders and restored the revision for decision on merits (paras 7-11).

Explanation for Delay Must Be Weighed Cumulatively: Supreme Court Restores DDA's Consumer Revision

Judgment Intelligence

Petition Allowed
Delhi Development Authority v. Sudarshan Manjhi & Ors.
2026 INSC 1254
Civil Appeal No. 14603 of 2026 (arising out of SLP (C) No. 9105 of 2025)
Court
Supreme Court of India
Date of Decision
20 November 2026
Bench
Justices Vikram Nath and Aparesh Kumar Singh
Relevant Acts & Sections
Constitution of India — Article 227 (petition before the High Court)
Final Outcome

Appeal allowed. The Delhi High Court's order of 23.10.2024 and the National Commission's order of 07.06.2024 are set aside; the delay in filing Revision Petition No. 1621 of 2022 is condoned and the revision restored for decision on merits after hearing the parties (paras 10-11).

Source Supreme Court of India, www.sci.gov.in — judgment dated 20 November 2026 · Court's copy

Key holdings

  1. The length of delay is not decisive; the acceptability of the explanation is the relevant consideration (para 6).
  2. With the Covid-19 exclusion of 15.03.2020 to 28.02.2022, only 95 days of DDA's delay needed explanation (para 7).
  3. Change of counsel or internal procedures cannot by themselves justify every delay, but the steps are weighed together (para 8).
  4. The Court condoned the delay while expressly not approving DDA's lack of diligence (para 9).
  5. No opinion was expressed on the merits of the allotment dispute; all contentions are left open (para 11).

Judgment digest by NyayVidhan: a summary of the court's judgment, not its text. The judgment itself is the authoritative version.

Brief Facts

The respondents' predecessor-in-interest was allotted a flat under DDA's Expandable Housing Scheme, 1996, in a 1997 draw of lots. She denied receiving the demand-cum-allotment letter, and DDA informed her on 20.10.2003 that the allotment had been cancelled (paras 3.1-3.2). The District Forum dismissed her complaint alleging deficiency in service, but on 09.04.2021 the State Commission held that the letter had not been duly served and directed DDA to allot an alternative flat at the original allotment rates (paras 3.3-3.4). DDA's revision petition, filed on 02.12.2022, was reported to be 512 days late. The National Commission refused to condone the delay on 07.06.2024, and the Delhi High Court dismissed DDA's Article 227 petition on 23.10.2024 (paras 3.5-3.7).

Court's Findings

Relying on Katiji, the Court recalled that ‘sufficient cause’ must receive a liberal interpretation to advance substantial justice, and, relying on N. Balakrishnan, that the length of delay is not decisive: the acceptability of the explanation is. The approach must be pragmatic and justice-oriented without rendering the requirement meaningless (para 6). A substantial part of the 512 days stood excluded under the Court's suo motu orders for 15.03.2020 to 28.02.2022, as the National Commission itself acknowledged, leaving 95 days to be explained (para 7). That delay occurred while DDA obtained administrative approval, engaged a panel lawyer and procured the certified copy. DDA ought to have acted with greater diligence, and a change of lawyer or internal procedures cannot by themselves justify every delay, but the circumstances must be considered cumulatively. The explanation disclosed the steps taken, and nothing on record suggested the delay was deliberate or meant to secure an undue advantage. The District Forum and the State Commission had reached different conclusions, which also made an examination on merits appropriate (para 8). The National Commission's approach was unduly restrictive, and the High Court gave insufficient weight to the cumulative circumstances (para 9).

Legal Principle

In deciding whether sufficient cause is shown, the acceptability of the explanation, not the length of delay, is decisive. Steps such as administrative approval, engaging a lawyer and obtaining a certified copy are weighed cumulatively; where the delay is not deliberate, a challenge may be heard on merits despite a lack of diligence (paras 6, 8-9).

NyayVidhan's view · Practice note

Why It Matters

An authority seeking condonation should set out each step it took, such as the administrative approval, the engagement of panel counsel and the date the certified copy was obtained. The Court weighed those steps together and found nothing deliberate, while recording that a change of counsel or internal procedures cannot by themselves justify every delay (para 8). Where the Covid-19 exclusion applies, only the delay left after excluding 15.03.2020 to 28.02.2022 needs explaining (para 7). On restoration, the National Commission is to decide the revision on merits after hearing the parties; the Supreme Court expressed no view on the allotment dispute (para 11).

Editorial comment by the NyayVidhan Editorial Desk. It is not part of the Court's judgment and is not legal advice.

Precedents Relied Upon

  1. Collector, Land Acquisition, Anantnag and Another v. Mst. Katiji and Others (1987) 2 SCC 107
    Relied Upon Discussed at ¶ 6

    The expression ‘sufficient cause’ must receive a liberal interpretation so as to advance substantial justice. Relied on for the settled principles of condonation of delay, applied to find sufficient cause for DDA's delay in filing its revision petition before the National Commission.

  2. N. Balakrishnan v. M. Krishnamurthy (1998) 7 SCC 123
    Relied Upon Discussed at ¶ 6

    The length of delay is not decisive; the acceptability of the explanation furnished is the relevant consideration. Relied on, with Katiji, for a pragmatic and justice-oriented approach that does not render the requirement of sufficient cause meaningless.

  3. In Re: Cognizance for Extension of Limitation Suo Motu Writ Petition (Civil) No. 3 of 2020
    Applied Discussed at ¶ 7

    The period from 15.03.2020 to 28.02.2022 was directed to be excluded for computing limitation. Applied to exclude a substantial part of the 512 days reported for DDA's revision petition, as the National Commission itself acknowledged, leaving 95 days to be explained.