Petition Allowed- Court
- Supreme Court of India
- Date of Decision
- 18 November 2026
- Bench
- Justices Dipankar Datta and Satish Chandra Sharma
- Relevant Acts & Sections
- Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 — Sections 2(1), 2(2)(b), 4, 5, 7, 8, 41, 103; Odisha Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Rules, 2016 — Rules 21, 41; Mines and Minerals (Development & Regulation) Act, 1957 — Section 24A; Constitution of India — Fifth Schedule
Writ petition allowed: the land acquisition, with the relevant notifications and orders, and the High Court's judgment are set aside (para 58). The State may begin a fresh acquisition in accordance with law and the judgment's findings (para 59). Appeal disposed of (para 60).
Source Supreme Court of India, www.sci.gov.in — judgment dated 18 November 2026 · Court's copy
Key holdings
- The purpose of acquisition, not who acquires or owns the land, decides between Section 2(1) and 2(2) (paras 26-27).
- Affected families' consent must be prior; subsequent consent cannot be justified (paras 31, 33-34).
- Section 41(3) Gram Sabha consent is mandatory; ‘as far as possible’ and ‘demonstrable last resort’ do not dilute it (paras 38-39).
- A person linked to the requiring company cannot sit on the independent Expert Group (paras 46-47).
- A mining lease governs only the State–lessee relationship and cannot override the landowners' proprietary rights (para 49).
Judgment digest by NyayVidhan: a summary of the court's judgment, not its text. The judgment itself is the authoritative version.
Brief Facts
Court's Findings
Legal Principle
NyayVidhan's view · Practice note
Why It Matters
For acquisitions for private projects, the ruling fixes an order of steps: the prior consent of affected families in the prescribed form (Form J under the Odisha Rules), taken along with the Social Impact Assessment, before the government examines the proposal under Section 8 (paras 28-33). In Scheduled Areas the Gram Sabha's consent must precede any notification, and its refusal cannot be bypassed (paras 37, 41). Those challenging an acquisition should check the Expert Group's members for links to the requiring body (paras 46-47) and the record of the public hearing (para 44). A fresh acquisition remains open, in accordance with law and the judgment's findings (para 59).
Editorial comment by the NyayVidhan Editorial Desk. It is not part of the Court's judgment and is not legal advice.