Judgment Intelligence
Petition Allowed
Vyakti Vikas Kendra India v. Manoj Misra (Dead) & Ors.
2026 INSC 910
Civil Appeal No. 683 of 2018
- Court
- Supreme Court of India
- Date of Decision
- 22 August 2026
- Bench
- Justice Satish Chandra Sharma and Justice Nongmeikapam Kotiswar Singh
- Relevant Acts & Sections
- National Green Tribunal Act, 2010 — Sections 15, 17
Final Outcome
Appeal disposed of. The NGT's judgment of 07.12.2017 is set aside with all consequential and interim actions against the appellant; DDA must refund the Rs. 5 crore deposit within four weeks and continue rehabilitating the Yamuna floodplain as directed by the Tribunal (paras 56-57).
Source Supreme Court of India (sci.gov.in), decided 22.08.2026
Judgment digest by NyayVidhan: a summary of the court's judgment, not its text. The judgment itself is the authoritative version.
Brief Facts
Respondent no. 1 moved the NGT on 08.02.2016 against the festival, held from 11 to 13 March 2016 on 25 hectares of the active Yamuna floodplain with DDA's permission (paras 2, 25-26). On 09.03.2016, two days before the event, the Tribunal relied on an expert committee's report of 22.02.2016, let the event go ahead subject to Rs. 5 crore as environmental compensation, and required an undertaking to bear the cost of restoration (paras 3, 27, 29). On 07.12.2017 it held the appellant responsible for restoration, the work to be done by DDA from the deposit (paras 12-13). The appellant said the site was already damaged when allotted; DDA said it had spent Rs. 8.03 crore on restoration (paras 15, 21).
Court's Findings
The only issue was whether the appellant damaged the floodplain and must restore it; the legality of DDA's permission was not before the Court (para 25). The 22.02.2016 report only described the site's condition and did not show it was better before the preparations; earlier reports, the Tribunal's own order of 14.07.2015 and DDA's December 2015 permission to remove debris showed it was already damaged (paras 29-31). The Tribunal wrongly treated its interim order, made without prejudice, as final: "The findings in an interim order are interim for a reason" (paras 33-36). The committee's satellite image of 05.09.2015 was unreliable, and its 28.11.2016 report admitted that the pre-event state could not be assessed (paras 41-42). By ordering rehabilitation and a biodiversity park, the Tribunal equated rehabilitation with restoration and exceeded its jurisdiction under Section 15 of the NGT Act (paras 46-48). It also rejected, without any challenge to its facts, an officials' committee report of 28.07.2017 that found little change after the event (paras 49-50). Section 17(3) applies to accidents, and no causal link was shown (paras 52-53).
Legal Principle
The polluter pays principle makes a polluter absolutely liable, but only once real environmental damage and a causal link between the project proponent's actions and that damage are established. Findings in an interim order passed without prejudice cannot decide liability finally, and the NGT's power of restoration under Section 15 does not extend to rehabilitation (paras 34, 47, 53).