Join our WhatsApp Group
Breaking
Friday, October 2, 2026 Jaipur Edition
Supreme Court of India
Constitutional Law

Disputed Overpayment Cannot Be Recovered From Bills Under Other Contracts Without Hearing: Supreme Court

The Supreme Court quashed a Chhattisgarh rural roads agency order that withheld Rs 84.17 lakh from a contractor's bills under three ongoing PMGSY contracts to recover an alleged overpayment on earlier, separate works. None of the contract clauses relied on authorised it, the audit clause required a hearing and the CEO's orders, and an unadjudicated claim is not a debt presently due.

Disputed Overpayment Cannot Be Recovered From Bills Under Other Contracts Without Hearing: Supreme Court
Photo: Subhashish Panigrahi via Wikimedia Commons (CC BY-SA 4.0)

Judgment Intelligence

Petition Allowed
M/s Awadhesh Singh Gautam v. State of Chhattisgarh & Ors.
2026 INSC 1072
Civil Appeals arising out of SLP (C) Nos. 10464, 12766 and 12346 of 2026
Court
Supreme Court of India
Date of Decision
30 September 2026
Bench
Justices Pamidighantam Sri Narasimha and Alok Aradhe
Relevant Acts & Sections
Constitution of India – Article 226; Chhattisgarh Land Revenue Code, 1959 – Section 146
Final Outcome

Appeals allowed. The recovery order dated 27.09.2025 was quashed and the respondents were directed to release Rs 84,17,003 with interest at 6% a year from 27.09.2025, without prejudice to lawful recovery proceedings or the pending criminal case (paras 28-30).

Key holdings

  1. A cross-contract recovery must be traceable to a specific clause whose preconditions are actually satisfied (para 24).
  2. An audit-recovery clause requiring a hearing and the CEO's orders cannot be bypassed by an Executive Engineer's unilateral order (para 23.1).
  3. An alleged overpayment, until established in law, is an unadjudicated claim for damages, not a debt presently due (para 25).
  4. Whether a contract authorises a recovery is a question of construction that a writ court can decide, not a disputed question of fact (paras 26-27).

Brief Facts

The appellant firm executed two earlier road contracts and, later, three PMGSY packages for the Chhattisgarh Rural Road Development Agency (paras 3-5). A committee found Rs 2.01 crore overpaid on the earlier works, and a demand note under Section 146 of the Chhattisgarh Land Revenue Code was quashed by the High Court in March 2025 for want of a hearing (paras 6-8). An FIR was registered against the firm's partner (para 9). On 27.09.2025 the Executive Engineer blocked Rs 84,17,003 from bills under the three later contracts (para 10). The High Court dismissed the writ petitions on 07.01.2026 as raising disputed facts (para 12).

Court's Findings

The Court examined each clause the State relied on (para 18). Clause 44.1 of the General Conditions covers only liquidated damages for delay, capped at 10% (para 19.1). Clause 53.1(ii) applies only after termination for breach of defects-liability and maintenance obligations, which never happened (para 20.1). Clause 7(iv) of the Integrity Pact presupposes a finding that the pact was violated, and the order neither cited it nor recorded one (para 21.1). Clause 38 requires the breach to be ascertained and the contractor told first (para 22.1). Clause 4.1 of the Special Conditions, the only audit-recovery clause, allows recovery from the audited work's own account, where about Rs 1.07 crore was still due, and requires a hearing, the CEO's orders and action within twelve months of completion; none was shown (para 23.1). Until established, the alleged overpayment is a disputed claim for damages, not a debt presently due, and cannot be appropriated from sums payable under a separate contract (para 25). The High Court erred, since the question turned on construing the contract, not on disputed facts (paras 26-27).

Legal Principle

An employer cannot appropriate amounts payable under one contract towards an alleged overpayment under another unless a clause clearly authorises it and its conditions, including notice and hearing, are met. An unadjudicated claim for damages is not a debt presently due.

Precedents Relied Upon

  1. Union of India v. Raman Iron Foundry (1974) 2 SCC 231
    Relied Upon Discussed at ¶ 25

    Until established in accordance with law, a claim for damages is a disputed, unadjudicated claim and not a debt presently due.

  2. ABL International Ltd. & Anr. v. Export Credit Guarantee Corporation of India Ltd. & Ors. (2004) 3 SCC 553
    Referred To Discussed at ¶ 14

    Relied on by the appellant (paras 26-28 of that report).

  3. Caretel Infotech Ltd. v. Hindustan Petroleum Corporation Limited (HPCL) & Ors. (2019) 14 SCC 81
    Referred To Discussed at ¶ 15

    Relied on by the State (para 24 of that report) in support of contractual set-off and recovery.

View all precedents (8)
  1. Bharti Airtel Ltd. & Anr. v. Vijaykumar V. Iyer & Ors. (2024) 4 SCC 668
    Referred To Discussed at ¶ 15

    Relied on by the State (paras 15-19 of that report) in support of contractual set-off and recovery.

  2. State of Gujarat & Anr. v. Amber Builders (2020) 2 SCC 540
    Referred To Discussed at ¶ 15

    Relied on by the State (paras 20-21 of that report) in support of contractual set-off and recovery.

  3. H.M. Kamaluddin Ansari and Co. v. Union of India & Ors. (1983) 4 SCC 417
    Referred To Discussed at ¶ 15

    Relied on by the State (paras 29 and 31 of that report) in support of contractual set-off and recovery.

  4. Nabha Power Limited (NPL) v. Punjab State Power Corporation Limited (PSPCL) & Anr. (2018) 11 SCC 508
    Referred To Discussed at ¶ 15

    Relied on by the State (para 72 of that report) in support of its reading of the contract.

  5. Union of India & Ors. v. N. Murugesan & Ors. (2022) 2 SCC 25
    Referred To Discussed at ¶ 15

    Relied on by the State (para 26 of that report) for the submission that a party cannot take the benefit of a contract while disowning its burden.

Nyay Vidhan
Court Judgments · 2 min read
Decided: September 30, 2026 Justices Pamidighantam Sri Narasimha and Alok Aradhe
PDF
WhatsApp Telegram X / Twitter LinkedIn

✕

Popular: POCSO, IBC, Electoral Bond, Article 370, NDPS Act, Bail Conditions, SC Contempt